Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change: Provided, however, That the Contracting Officer, If he decides that the facts justify... NHB. - Page 7661970Full view - About this book
| Administrative law - 1960 - 890 pages
...Any claim by the Contractor for adjustment under this clause must be asserted within sixty (60) days from the date of receipt by the Contractor of the...justify such action, may receive and act upon any claim asserted at any time prior to final payment under this contract. Where the cost of property made... | |
| Administrative law - 1960 - 260 pages
...within 30 days from the date of receipt by the Contractor of the notification of change: Proi'ided. however. That the Contracting Officer, if he decides...act upon any such claim asserted at any time prior t^i final payment undei this contract. Where the cost of property made obsolete or excess as a result... | |
| United States. Department of the Army - Government purchasing - 1961 - 346 pages
...under this clause must be asserted within 30 days from the date of receipt by Her Majesty's Government of the notification of change : provided, however,...asserted at any time prior to final payment under this Agreement. 3. Extras Except as otherwise provided in this Agreement, no payment for extras shall be... | |
| United States. Department of the Army - Defense contracts - 1961 - 464 pages
...within 30 days from the date of receipt by the Contractor of the notification of change: provi&eA, however, that the Contracting Officer. if he decides...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's... | |
| Administrative law - 1963 - 814 pages
...Any claim by the Contractor for adjustment under this clause must be asserted within sixty (60) days from the date of receipt by the Contractor of the...justify such action, may receive and act upon any claim asserted at any time prior to final payment under this contract. Where the cost of property made... | |
| Administrative law - 1963 - 864 pages
...accordingly. Any claim by the Contractor for adjustment undei this clause must be asserted within .3(1 da> s from the date of receipt by the Contractor of the...he decides that the facts justify such action, may u-ceivc and act upon any such claim asserted at any time prior to final payment under this contiact.... | |
| United States. Congress. Joint Committee on Atomic Energy - Public contracts - 1964 - 379 pages
...Any claim by the Contractor for adjustment under this Article XVII must be asserted within 60 days from the date of receipt by the Contractor of the...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's... | |
| United States. Congress. House. Education and Labor - 1964 - 112 pages
...asserted within 30 days from the date of receipt by the Contractor of the notification of charigei Provided, however, That the Contracting Officer, if...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's... | |
| |