... Plant and equipment of the right capacity and reliability must be ready for service neither too early nor too late . It is thus necessary that the growth of demand be estimated accurately year by year and the installation of plant ...
... Plant and equipment of the right capacity and reliability must be ready for service neither too early nor too late . It is thus necessary that the growth of demand be estimated accurately year by year and the installation of plant ...
Page 13
... Plant and equipment of the right capacity and reliability must be ready for service neither too early nor too late . It is thus necessary that the growth of demand be estimated accurately year by year and the installation of plant ...
... Plant and equipment of the right capacity and reliability must be ready for service neither too early nor too late . It is thus necessary that the growth of demand be estimated accurately year by year and the installation of plant ...
Page 19
Great Britain. Parliament. House of Commons. CHAPTER 2 POWER STATIONS : PLANT AND PROGRAMMES This chapter deals with generating capacity , the plant programmes , plant design and development , and some aspects of power station operation ...
Great Britain. Parliament. House of Commons. CHAPTER 2 POWER STATIONS : PLANT AND PROGRAMMES This chapter deals with generating capacity , the plant programmes , plant design and development , and some aspects of power station operation ...
Contents
Electricity Supply Industry in England and Walesmaps | 1 |
GENERATION TRANSMISSION AND DISTRIBUTION | 13 |
DIAGRAMS | vii |
156 other sections not shown
Other editions - View all
Common terms and phrases
1st April Alderman amount Appendix appliances Area Boards average Balance Sheet bulk supply cent Central Electricity charges Commercial commissioned Committee connected Contracting and Sales contributions Councillor Denbighshire depreciation Deputy Chairman District domestic East Midlands East Midlands Electricity Eastern Electricity Board Electricity Act Electricity Consultative Council Electricity Council Electricity Generating Board electricity supply employees ended 31st March farms fixed assets Grid hire purchase included Income increase installed kilowatts liabilities load factor LONDON ELECTRICITY BOARD maximum demand Merseyside Merseyside and North meter reading MIDLANDS ELECTRICITY BOARD Minister of Power North Eastern Electricity North Wales nuclear off-peak operation organisation overhead lines paragraph plant power stations premises programme provision Public Lighting rates reduced Report Revenue Account Road sales of electricity Sales of Fittings Scheme Section service centres South staff steam Street Sub-Area substation sumers Superannuation surplus Tariff unit sold volt transformer voltage volts wayleaves