| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1962 - 784 pages
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the..."Disputes." However, nothing in this clause shall excuse the Con148 c. Os. Per Cariam tractor from proceeding with the contract as changed. * * * * * 12. DISPUTES... | |
| Administrative law - 1969 - 790 pages
...cost or delivery schedule, or both, (2) in the amount of any fee to be paid to the Contractor, and (3) in such other provisions of the contract as may be...to any adjustment shall be a dispute concerning a question oí fact within the meaning of the clause oí this contract entitled "Disputes". However,... | |
| Administrative law - 1972 - 914 pages
...cost or delivery schedule, or both, (2) In the amount of any fee to be paid to the Contractor, and (3) In such other provisions of the contract as may be...to any adjustment shall be a dispute concerning a question of fact within the meaning of the clause of thla contract entitled "Disputes". However, nothing... | |
| Administrative law - 1972 - 914 pages
...cost or delivery schedule, or both, (2) in the amount of any fee to be paid to the Contractor, and (3) in such other provisions of the contract as may be...contract. Failure to agree to any adjustment shall bea dispute concerning a question of fact within the meaning of the clause of this contract entitled... | |
| Administrative law - 1980 - 976 pages
...Any claim by the Contractor for adjustment under this clause must be asserted within sixty (6O) days from the date of receipt by the Contractor of the..."Disputes." However, nothing In this clause shall excuse th« Contractor from proceeding with the contract as changed. (End of clause) NASA PROCUREMENT REGULATION... | |
| Administrative law - 1984 - 720 pages
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the...clause of this contract entitled "Disputes." However, except as provided in paragraph (c>, below, nothing In this clause shall excuse the Contractor from... | |
| Administrative law - 1982 - 532 pages
...Contractor for adjustment under this clause must be asserted within thirty (30) days from the date or receipt by the Contractor of the notification of change;...to any adjustment shall be a dispute concerning a question of fact within, the meaning of the "Disputes" clause of this contract. However, nothing in... | |
| Administrative law - 1979 - 520 pages
...Contractor for adjustment under this clause must be asserted within thirty (30) days from the date or receipt by the Contractor of the notification of change;...to any adjustment shall be a dispute concerning a question of fact within, the meaning of the "Disputes" clause of this contract. However, nothing in... | |
| Administrative law - 1978 - 944 pages
...Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor of the...contract. Failure to agree to any adjustment shall be • dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract.... | |
| Administrative law - 1977 - 944 pages
...by the Contractor of the notification of change: Prodded, however, That the Contracting Officer, It he decides that the facts justify such action, may...clause of this contract entitled "Disputes." However, except as provided In paragraph (c), below, nothing In this clause shall excuse the Contractor from... | |
| |