| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1941 - 966 pages
...the Court ceeding under this clause, the contractor shall be afforded an opportunity to be heard and offer evidence in support of his appeal. Pending final decision of a dispute hereunder, the contractor shall proceed diligently with the performance of the contract and in accordance with... | |
| Administrative law - 1974 - 640 pages
...any appeal proceeding under this clause, the Contractor shall be afforded an opportunity to be heard and to offer evidence in support of his appeal. Pending final decision of a dispute hereunder, the Contractor shall proceed diligently with the performance of the contract and In accordance with... | |
| Administrative law - 1978 - 944 pages
...appeal proceeding under this clause, the Architect-Engineer shall be afforded an opportunity to be heard and to offer evidence in support of his appeal. Pending final decision of a dispute hereunder, the Architect-Engineer shall proceed diligently with the performance of the contract and in accordance... | |
| Administrative law - 1976 - 1202 pages
...any appeal proceeding under this clause, the Contractor shall be afforded an opportunity to be heard and to offer evidence in support of his appeal. Pending final decision of a dispute hercunder, the Contractor shall proceed diligently with the performance of the contract and in accordance... | |
| Administrative law - 1981 - 524 pages
...any appeal proceedings under this clause, the Contractor shall be afforded an opportunity to be heard and to offer evidence in support of his appeal. Pending final decision of a dispute liereundcr, the Contractor shall proceed diligently with the performance of Ihc contract and in accordance... | |
| Administrative law - 1979 - 1078 pages
...any appeal proceeding under this clause, the Contractor shall be afforded an opportunity to be heard and to offer evidence in support of his appeal. Pending final decision of a Title 41 — Public Contracts, Property Management dispute hereunder. the Contractor shall proceed... | |
| Administrative law - 1976 - 888 pages
...any appeal proceeding under this Section, the appellant shall be afforded an opportunity to be heard and to offer evidence in support of his appeal. Pending final decision of a disputó hereunder, both parties shall proceed diligently with the performance of the Contract and... | |
| Administrative law - 1972 - 914 pages
...any appeal proceeding under this clause, the Contractor shall be afforded an opportunity to be heard and to offer evidence In support of his appeal. Pending final decision oí a dispute hereunder, the Contractor shall proceed diligently with the performance or the contract... | |
| Administrative law - 1978 - 1966 pages
...under this Section, the appellant shall be afforded an opportunity to be heard and to offer ev.dence in support of his appeal. Pending final decision of a dispute hereunder, both parties shall proceed diligently with the performance of the Contract and in accordance with the... | |
| United States. Congress. House. Committee on the Judiciary - 1955 - 292 pages
...appeal under this "Disputes" clause the Contract Architect shall be afforded an opportunity to be heard and to offer evidence in support of his appeal. Pending final decision of a dispute hereunder, including adjudication of any litigation in connection with such decision, the Contract Architect shall... | |
| |