be filed with the Federal Power Commission. Two conformed copies are to be filed with the commission of each State which is wholly or partly within the geographic boundaries of the reporting council. Reports are to be filed not later than April 1 of each year, except that for the base year 1970 the reporting date is extended to September 1, 1970. Councils which have not yet completed their organizational structure and procedures are requested to furnish by September 1, 1970, as much data as is readily available, and to furnish the balance at the earliest practicable date thereafter.

(C) The amendments prescribed herein will be effective upon the issuance of this order.

By the Commission.

(SEAL)

31-256 O-71 - 11 (pt. 2)

Gordon M. Grant,
Secretary.

APPENDIX A

INFORMATION TO BE REPORTED BY REGIONAL COUNCILS ON
COORDINATED REGIONAL BULK POWER SUPPLY PROGRAMS

Information, to be reported annually except as otherwise noted, should include:

1. Estimates of monthly peak loads for the first two years of the projection; estimates of summer and winter peak loads for the remaining eight years; and monthly energy requirements for the first two years if energy substantially influences planning and operation.

2. Itemization of all existing capacity resources in the region
and new capacity resources (or retirements) as committed or
projected for each year ten years into the. future; including,
where known, in-service dates, locations, ownership, and
types of future generating units, and capacity exchanges
with others at the time of summer and winter peak demands.

3. For each year of the ten-year projection, show the indicated capacity margins for reserves at the time of summer and winter peak loads, based on Items (1) and (2) above, with an assessment of adequacy of reserves for the first five years of the projection. Include a statement of the criteria now being used in determining reserve requirements by the Council or its appropriate subdivisions.

4. For each steam generating unit of 300 mw or more, and for which construction has begun; or is scheduled to begin within two years from the date of reporting, a status report on the proposed plan of cooling, and for fossil-fired plants, the fuels proposed and the plan for controlling stack emissions; also, the status of principal studies or model tests and the status of consultations with appropriate local, State or Federal authorities concerned.

5. A plan of the bulk power transmission network of the region in service at the time of the report, (including interties with adjoining regions) and the general routing of facilities committed or tentatively projected for service within six years including identification of principal substations, operating voltages and projected in-service dates. In addition, show the transmission facilities projected for the balance of the ten-year period based upon the best information available.

6. A plotting and a description of the base case for load flow studies of the bulk power network of the region (or principal subdivisions) as it exists, substantially, at the time of reporting and as projected four to six years in the future; and a tabulation and brief statements on the results of a representative number of contingency cases studied; and similarly, information on stability analyses of the network, and including the criteria adopted by the regional council relating to network stability.

7. A description of the principal communication and control systems operating or planned within the region and listing of functions performed by such facilities. (To be reported initially and updated in subsequent reports when significant changes occur.)

8. For each transmission segment designed to operate at 230 kv (nominal) or higher for which construction has begun or is scheduled to begin within two years from the date of the report, information on the status of consultations with affected local communities and groups, and status of applications to State or regional authorities, as appropriate.

9.

Information on the following coordinated regional practices: (To be reported initially and updated in subsequent reports when significant changes occur.)

a. Load shedding programs, including estimated steps of load reduction at various steps in declining frequency.

b.

C.

d.

e.

f.

8.

Emergency power and shutdown facilities to prevent
damage to equipment if station loses system power.

Power facilities available for unit startup in the
event of total loss of system power.

Availability of continuous power independent of system sources for communication and control facilities.

Provisions for sustaining the operation of generating
units on local loads.

Programs for scheduling maintenance outages of generation and transmission facilities.

Programs for the selection, setting and maintenance of relays that affect the overall reliability of the interconnected network.

APPENDIX D

Load Supply Tabulations for 1970 Summer Peak Period

FEDERAL POWER COMMISSION
REGIONAL OFFICE

610 South Canal Street, Room 1051

Chicago, Illinois 60607

MEMORANDUM TO ALL UTILITIES IN THE WEST CENTRAL REGION
SUBMITTING REPORTS ON THE FPC MONTHLY FORM 12-E

May 1970

Attached for your information is a summary analysis of the reported loads and available supply of electric utilities in the West Central Region during the coming summer peak season, June through September 1970. The Region consists of the Federal Power Commission designated Power Supply Areas 13, 14, 15, 16, 17, 26, 27, 28 and 40. This includes all of the states of Illinois, Iowa, Minnesota, North Dakota, South Dakota, and Wisconsin; and parts of Michigan, Missouri, Montana, Nebraska and Wyoming. The attached map shows the geographical location of the area.

The enclosed tabulation is based primarily on data reported by the principal electric systems or pools in the Region to the Commission on FPC Form No. 12-E, Monthly Power Statement, for January 1970. The Iowa pool, consisting of six utilities, submits a consolidated Form 12-E report. The 12-E reporting systems represent the major portion of the total utility capacity and energy requirements in the Region.

The tabulation compares estimated 1970 summer peaks with generating capacity expected to be in service at the end of May 1970, increased or decreased by firm purchases or obligations expected to be in effect at the time of the summer peak.

Since the cut-off date for capacity additions is the end of May, supplemental tabulation is included showing scheduled capacity changes during June, July and August. If scheduled additions become commercially available for service by the time of the summer peak, the figures on capacity available for reserves should be adjusted accordingly.

The summaries reflect only those intersystem transfers that are reported to be covered by firm contracts. No endeavor has been made to account for emergency measures that might be resorted to for the purpose of matching power requirements and supply, such as dropping interruptible loads and reducing voltage. Likewise, no reduction in dependable capacity has been considered due to scheduled maintenance of units or other factors.

To ensure the probability that system load demands can be met, sufficient capacity must be provided not only to meet the expected peaks of the load but also to provide adequate reserve capacity to compensate for forced outages, required maintenance, and other reasonable contingencies. Many systems plan reserves in an amount which may range from about 10 to 20 percent of the expected system peak load demands.

The West Central Region as a whole has an indicated reserve margin of 4,371 megawatts or 12.7 percent of the estimated summer peak. The indicated reserves for a number of the reporting systems appear to be marginal. Furthermore, some of the margins are dependent upon imports from external systems during peak load periods. Based on actual system capacity, it appears that some systems will not have sufficient reserves of their own during the coming summer. The Union Electric Company, in PSA 15, showing less than one percent capacity available for reserves, has 555 mw of new capacity scheduled to be in service by the time of its system's peak.

This addition (Labadie Unit #1-Fossil Steam), which will increase the capacity available for reserves to 14.1 percent, is expected to contribute to system load beginning in May. Similarly, the Northern States Power Company has a 460 mw capacity addition (Monticello #1 Unit-Nuclear) scheduled to be in service by the time of its system peak in July. Capacity available for reserves will then increase to 12.1 percent. The possible dependence of these systems on power imports from other utilities makes it imperative that operations be coordinated adequately to ensure the availability of supplemental power when needed. The coordination arrangements will need to cover both the availability of standby generation on the interconnected systems and operational planning to maintain network loading which will permit the required power transfers to meet peak loads and maintain adequate transmission reserves.

[ocr errors]

While only firm purchases and sales have been included, additional capacity can be made available through interconnected systems within the Region on a non-firm, short-term basis if an emergency should develop. When reviewing the probability that system load can be met, consideration must be given to other potential factors. Among these are, labor developments such as the recent General Electric Company strike affecting inservice dates of critical generating and transmission facilities, fuel supplies as affected by source and transportation problems, weather conditions contributing to outages or reduction in system output, and simultaneous outages of large increments of system capacity.

A copy of this memorandum and the tabulation is being furnished to each State Commission in the West Central Region and to each utility in the Region which reports or participates in reporting on the FPC Monthly Form 12-E.

Attachments:
Tabulation

NPS Regions Map

Benard

Lenard B. Young
Regional Engineer