" The Contracting Officer shall ascertain the facts and the extent of the delay and extend the time for completing the work when, in his judgment, the findings of fact justify such an extension. "
The Code of Federal Regulations of the United States of America - Page 371
1980
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 111

United States. Court of Claims - Law reports, digests, etc - 1948 - 886 pages
...longer period as may be allowed by the Contracting Officer, notify the Contracting Officer in writing of the causes of delay. The Contracting Officer shall...judgment the findings of fact justify such an extension. The decision of the Contracting Officer thereon shall be final, subject only to appeal under Article...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 115

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1950 - 940 pages
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...judgment the findings of fact justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 114

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1950 - 824 pages
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...his judgment the findings of fact justify such an extensionj and his findings of fact thereon shall be final and conclusive on the parties hereto, subject...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 104

United States. Court of Claims - Law reports, digests, etc - 1946 - 936 pages
...contract) notify the contracting officer in writing of the causes 01 delay, who shall ascertain the fact and the extent of the delay and extend the time for...judgment the findings of fact justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 152

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1963 - 938 pages
...longer period as may be allowed by the Contracting Officer, notify the Contracting Officer in writing of the causes of delay. The Contracting Officer shall...delay and extend the time for completing the work or any part thereof when in his judgment the findings of fact justify such an extension. The decision...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volumes 110-120

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1952 - 932 pages
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...completing the work when in his judgment the findings of tact justify such an extension, and his findings of fact thereon shall be final and conclusive on the...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 123

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1958 - 1044 pages
...notify the contracting officer in writing of the causes of the delay, who shall ascertain the facts and extent of the delay and extend the time for completing...judgment the findings of fact justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only...
Full view - About this book

Decisions of the Comptroller General of the United States, Volume 29

United States. General Accounting Office - Finance, Public - 1950 - 710 pages
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...judgment the findings of fact justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only...
Full view - About this book

The Code of Federal Regulations of the United States of America ..., Book 2

Administrative law - 1939 - 1306 pages
...final settlement of the contract) notify the contracting officer In writing of the causes of delay, who shall ascertain the facts and the extent of the delay...Judgment the findings of fact Justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1978 - 880 pages
...Contractor's right to proceed with the work is terminatChapter 4 — Department of Agriculture ed, he and his sureties shall be liable for any damage...beginning of the delay, the contractor shall have 10 days from the beginning of any such delay (unless the Contracting Officer grants a further period of...