Cases Decided in the Court of Claims of the United States, Volume 111U.S. Government Printing Office, 1948 - Law reports, digests, etc |
From inside the book
Results 1-5 of 65
Page 389
... cofferdam , as well as the necessity for changing the drainage system , the hard driving of wooden piles and the necessity for the use of steel sheet piles ; it is held that under the provisions of the contract , the contractor was ...
... cofferdam , as well as the necessity for changing the drainage system , the hard driving of wooden piles and the necessity for the use of steel sheet piles ; it is held that under the provisions of the contract , the contractor was ...
Page 390
... cofferdam . Same ; claim as to concrete . - Where , under the orders of the Govern- ment's agents who had the power to determine what the content of the concrete mix should be , the plaintiff placed a quantity of Class A concrete around ...
... cofferdam . Same ; claim as to concrete . - Where , under the orders of the Govern- ment's agents who had the power to determine what the content of the concrete mix should be , the plaintiff placed a quantity of Class A concrete around ...
Page 392
... Cofferdam . 2. Excavation , piling foundations , and fill for the com- plete structures . 3. Concrete Masonry of the complete structures . 4. Mitering Lock Gates and Tainter Valves . 5. Operating Machinery . 6. Central Control Station ...
... Cofferdam . 2. Excavation , piling foundations , and fill for the com- plete structures . 3. Concrete Masonry of the complete structures . 4. Mitering Lock Gates and Tainter Valves . 5. Operating Machinery . 6. Central Control Station ...
Page 393
... cofferdam . That cofferdam consisted of three arms : An arm approximately 1,000 feet long generally parallel with the Illinois shore , known as the river arm ; an arm extending from the north end of the river arm to the Illinois shore ...
... cofferdam . That cofferdam consisted of three arms : An arm approximately 1,000 feet long generally parallel with the Illinois shore , known as the river arm ; an arm extending from the north end of the river arm to the Illinois shore ...
Page 396
... cofferdam . The specifications further provided that the contractor might build any other type cofferdam , with the approval of the contracting officer , which would provide protection and 389 Reporter's Statement of the Case have ...
... cofferdam . The specifications further provided that the contractor might build any other type cofferdam , with the approval of the contracting officer , which would provide protection and 389 Reporter's Statement of the Case have ...
Other editions - View all
Common terms and phrases
acre-feet additional alleged amended amount approximately April bales Bid Form bid Item change order channel cofferdam Commissioner compensation completed concrete construction contract price contracting officer contractor cost Court cubic yards December deduction defendant defendant's Defense Supplies Corporation Delaware delay delivery District drainage drawings East Side Canal entitled to recover excavation feet filed fiscal flood floor slabs flow follows Friant Dam Friant-Kern Canal furnished Government grading income installed inventory irrigation July July 26 June labor lands letter liquidated damages Lux Incorporated Madera Canal material ment Miller & Lux Mitchell Canneries October October 20 operation Opinion Overflow Survey paid payment percent performed period petition plaintiff Potter lands prior pumping raw silk Reporter's Statement request Revenue riparian rights Sacramento River San Joaquin River Schedule Section September September 16 Slough specifications Stat statute Swamp and Overflow taxable thereof tion tract unit price walls
Popular passages
Page 244 - The delay in the completion of the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor...
Page 617 - The net income of the estate or trust shall be computed in the same manner and on the same basis as in the case of an individual...
Page 376 - Except as otherwise provided in this contract, any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the Contracting Officer, who shall reduce his decision to writing and mail or otherwise furnish a copy thereof to the Contractor.
Page 618 - In the case of property held in trust, the allowable deduction shall be apportioned between the income beneficiaries and the trustee in accordance with the pertinent provisions of the instrument creating the trust, or, in the absence of such provisions, on the basis of the trust income allocable to each.
Page 608 - All children heretofore born or hereafter born out of the limits and jurisdiction of the United States, whose fathers were or may be at the time of their birth citizens thereof, are declared to be citizens of the United States ; but the rights of citizenship shall not descend to children whose fathers never resided in the United States.
Page 80 - State the general welfare requires that the water resources of the State be put to beneficial use to the fullest extent of which they are capable, and that the waste or unreasonable use or unreasonable method of use of water be prevented, and that the conservation of such waters is to be exercised with a view to the reasonable and beneficial use thereof in the interest of the people and for the public welfare.
Page 40 - Riparian rights in a stream or water course attach to, but to no more than so much of the flow thereof as may be required or used consistently with this section, for the purposes for which such lands are, or may be made adaptable, in view of such reasonable and beneficial uses ; provided, however, that nothing herein contained shall be construed as depriving any riparian owner of the reasonable use of water of the stream to which his land is riparian under reasonable methods of diversion and use,...
Page 396 - ... shall ascertain the facts and the extent of the delay and extend the time for completing the work when in his judgment the findings of fact justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto...
Page 497 - The Contractor shall keep on the work a copy of the drawings and specifications and shall at all times give the Contracting Officer access thereto. Anything mentioned in the specifications and not shown on the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both.
Page 638 - The taxpayer consents in writing to the assessment, within such period as may be agreed upon, of any deficiencies resulting from such treatment, even though the statutory period for the assessment of any such deficiency had expired prior to the filing of such consent.