... Average Period Average Period Plant Generating Generating Plant in Commis- Running sion in in 1958-9 * Amount Proportion of Total Amount Proportion of Total 1958-9 * per cent . MW per cent . thousand per cent . hours hours units 32 and ...
... Average Period Average Period Plant Generating Generating Plant in Commis- Running sion in in 1958-9 * Amount Proportion of Total Amount Proportion of Total 1958-9 * per cent . MW per cent . thousand per cent . hours hours units 32 and ...
Page 177
... Average Maximum Output Capacity Average Calorific Maximum Output Capacity at 31st March , in 1958-9 Value of Fuel Average Thermal Generating Plant Brought Efficiency into 1959 Operation ° F MW million units Castle Donington ( nr . Derby ) ...
... Average Maximum Output Capacity Average Calorific Maximum Output Capacity at 31st March , in 1958-9 Value of Fuel Average Thermal Generating Plant Brought Efficiency into 1959 Operation ° F MW million units Castle Donington ( nr . Derby ) ...
Page 7
... average for all area boards in 1958-59 the difference had shrunk to 11s . 4d . Stable average charge to consumers 110 100 90 80 AVERAGE PRICE PER TON [ SHILLINGS ] 69 16. Although in 1957-58 there was a loss on sales of electricity of ...
... average for all area boards in 1958-59 the difference had shrunk to 11s . 4d . Stable average charge to consumers 110 100 90 80 AVERAGE PRICE PER TON [ SHILLINGS ] 69 16. Although in 1957-58 there was a loss on sales of electricity of ...
Contents
Electricity Supply Industry in England and Walesmaps | 1 |
CONSUMER SERVICE SALES AND LOAD FACTOR | 15 |
Relations with Other Bodies | 25 |
Copyright | |
178 other sections not shown
Other editions - View all
Common terms and phrases
1st April 1st January 31st December Alderman allocated amount Appendix Area Boards Balance Sheet British Electricity Stock Bulk Supply Tariff capacity capital expenditure cent Central Electricity Central Electricity Authority Central Guarantee Fund charges Committee contributions Councillor Deputy Chairman District East Midlands Electricity Act Electricity Consultative Council Electricity Council Electricity Generating Board electricity supply employees ended 31st March England and Wales fifteen months ended financing expenses Fixed Assets Grid hire purchase increase installed kilowatts load factor LONDON ELECTRICITY BOARD main transmission maximum demand Merseyside MIDLANDS ELECTRICITY BOARD million Minister of Power Miscellaneous months ended 31st North Eastern Notes on Accounts operation organisation overhead lines paragraph payment period plant power stations premises programme provision respect Revenue Account Road sales of electricity Sales of Fittings schemes Section staff Sub-Area substation sumers Superannuation surplus Tariff Total Total stations transferred transformer tricity unit sold units per quarter voltage volts