Decisions of the Comptroller General of the United States, Volume 73U.S. Government Printing Office, 1994 - Finance Contains a selection of major decisions of the GAO. A digest of all decisions has been issued since Oct. 1989 as: United States. General Accounting Office. Digests of decisions of the Comptroller General of the United States. Before Oct. 1989, digests of unpublished decisions were issued with various titles. |
From inside the book
Results 1-5 of 63
Page 3
... estimated " as follows : USDA uses approximately 2,660,000 gallons of water per month . This is 87,300 gallons per day . As- suming 70 % of this water is discharged into the sewer an average of 61,100 gallons per day of sewage is ...
... estimated " as follows : USDA uses approximately 2,660,000 gallons of water per month . This is 87,300 gallons per day . As- suming 70 % of this water is discharged into the sewer an average of 61,100 gallons per day of sewage is ...
Page 26
... estimated to be approxi- mately 80 percent complete . On December 21 , 1992 , Orbital's contract was par- tially terminated for the convenience of the government ; this included the pro- gram for which Orbital was building the four ...
... estimated to be approxi- mately 80 percent complete . On December 21 , 1992 , Orbital's contract was par- tially terminated for the convenience of the government ; this included the pro- gram for which Orbital was building the four ...
Page 28
... estimated that Space Vector would re- quire approximately 12 to 18 months to fully integrate and test a GPS system , and that this would delay the October 1993 launch , which was considered to be • The contract authority to proceed date ...
... estimated that Space Vector would re- quire approximately 12 to 18 months to fully integrate and test a GPS system , and that this would delay the October 1993 launch , which was considered to be • The contract authority to proceed date ...
Page 29
... estimated 7 [ to ] 11 month [ delay in ] the production schedule " ; ( 2 ) the October 1993 launch date could not ... estimated life of 6 months . The agency states that historically the MSTI satellite's useful life has been shorter than ...
... estimated 7 [ to ] 11 month [ delay in ] the production schedule " ; ( 2 ) the October 1993 launch date could not ... estimated life of 6 months . The agency states that historically the MSTI satellite's useful life has been shorter than ...
Page 31
... estimated as taking 17 months . 20 This individual was admitted to the protective order to assist counsel for Space Vector . ་ ་ ་ ་ ལ་ ་ ་་་ ། ་ འ་ ་ ་ ་་་ ་་་ the Navy LEAP program had progressed to the point of Page 31 ( 73 Comp . Gen. )
... estimated as taking 17 months . 20 This individual was admitted to the protective order to assist counsel for Space Vector . ་ ་ ་ ་ ལ་ ་ ་་་ ། ་ འ་ ་ ་ ་་་ ་་་ the Navy LEAP program had progressed to the point of Page 31 ( 73 Comp . Gen. )
Other editions - View all
Common terms and phrases
70 Comp Administration agency agency's Air Force amended amount Antideficiency Act appropriation April 25 argues Army ARTI's authorized award BAFO basis bid opening Bid Protests bidder BMDO certified charges claim competitive range contends contracting officer contractor Corp cost court crankshaft decision denied determination duty station EER's employee entitled expenses Federal Federal Acquisition Regulation filed fiscal Fort Jackson Fort McPherson funds GPS receiver GSSC's improperly issued June launch LEAHY class cruisers ment Motorola obligation offerors OHIO STATE UNIVERSITY option payment Peat Marwick performance period personnel prior proposal protest protester's rates reasonable receipt regulations reimbursement request response schedule score sewer small business concerns solicitation Space Vector specific Stat subfactor submitted supra Swales's target vehicle technical tion Treasury check United unofficial travel USIA waiver