| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1963 - 938 pages
...notification of extra or change : Provided, however, That the contracting officer, if he decides that the facts justify such action, may receive, and act...upon any such claim asserted at any time prior to the date of final settlement of the contract. It the parties fail to agree upon the adjustment to be... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1968 - 922 pages
...of the notification of change : Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive and act upon any such claim asserted at any time/prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
| Administrative law - 1993 - 904 pages
...of the notification of change; provided, however, that the contracting officer, if he decides that the facts justify such action, may receive and act...the meaning of the clause entitled "Disputes." (b) \Vnrk to continue. Nothing contained in this clause shall excuse the contractor from proceeding with... | |
| Administrative law - 1982 - 1316 pages
...days from the date of receipt by the Contractor of the notification of change; provided, however, thai the Contracting Officer, if he decides thai the facts...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning... | |
| Administrative law - 1982 - 690 pages
...of the notification of change; Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive and act...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning... | |
| Administrative law - 1986 - 1072 pages
...of the notification of change: Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive and act...asserted at any time prior to final payment under the contract. Failure to agree to any adjustment shall be considered a dispute concerning a question... | |
| Administrative law - 1974 - 1028 pages
...notification of change: Provided, however, That the Contracting Officer, If he decides that the facts justIf¿ such action, may receive and act upon any such claim...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change Is included In the Contractor's... | |
| Administrative law - 1966 - 968 pages
...of the notification of change: Provided, however, That the Contracting Officer, If he decides that the facts justify such action, may receive and act upon any such claim asserted at any time prior to § 7.702-5 final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
| Administrative law - 1970 - 984 pages
...work stoppage: Provided, That, If the Contracting Officer decides the facts justify such action, he may receive and act upon any such claim asserted at...any time prior to final payment under this contract. (c) If a stop work order Is not canceled and the work covered by such order Is terminated for the convenience... | |
| Administrative law - 1977 - 722 pages
...work stoppage; provided that, if the contracting officer decides the facts justify such action, he nay receive and act upon any such claim asserted at any time prior to final payment under this contract. (c) If a stop work order is not cancelled and the work covered by such order is terminated for default,... | |
| |