" Where the cost of property made obsolete or excess as result of a change is included in the Contractor's claim for adjustment, the Contracting Officer shall have the right to prescribe the manner of disposition of such property. Failure to agree to any... "
The Code of Federal Regulations of the United States of America - Page 444
1969
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 148

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1962 - 784 pages
...receive and act upon any such claim asserted at any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute..."Disputes." However, nothing in this clause shall excuse the Con148 c. Os. Per Cariam tractor from proceeding with the contract as changed. * * * * * 12. DISPUTES...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1955 - 1316 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change:...must be asserted may be varied in accordance with Department procedures. CODIFICATION: § 7.103-2 was revised by Amendment 14, 21 FB 6410, Aug. 25, 1956,...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1982 - 532 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change....Contractor from proceeding with the contract as changed. § 15-7.150-2 Inspection of services. Insert the following clause only in service contracts other than...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1979 - 1186 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change,...Contractor from proceeding with the contract as changed. (End of cbiuel In the foregoing clause, the period of "30 days" within which any claim for adjustment...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1975 - 1236 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change,...Contractor from proceeding with the contract as changed. (End of clause) In the foregoing clause, the period of "30 days" within which any claim for adjustment...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1970 - 984 pages
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date or receipt by the Contractor of...entitled "Disputes". However, nothing In this clause •hall excuse the Contractor from proceeding with the contract as changed. In the foregoing clause,...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1982 - 712 pages
...prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's...the contract as changed. In the foregoing clause the pehod of "30 days" within which any claim for adjustment must be asserted may be varied not to exceed...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1981 - 676 pages
...prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's...Contractor from proceeding with the contract as changed. § 1-7.102-3 Extras. EXTRAS Except as otherwise provided in this contract, no payment for extras shall...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1993 - 664 pages
...prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's...Contractor from proceeding with the contract as changed. (End of clause) CLAUSE No. 20— RETROCESSION (JUNE 1977) (a) The Indian tribe that initially requested...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1971 - 664 pages
...prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's...Contractor from proceeding with the contract as changed. 3. EXTRAS Except as otherwise provided in this contract, no payment for extras shall be made unless...