" Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change: Provided, however. That the Contracting Officer, if he decides) that the facts justify such action, may... "
Code of Federal Regulations: Containing a Codification of Documents of ... - Page 228
1977
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1979 - 712 pages
...work stoppage; provided that, if the Contracting Officer decides the facts justify such action, he may receive and act upon any such claim asserted at any...shall be allowed by equitable adjustment or otherwise. §9-7.203 Clauses to be used when applicable. This section prescribes modifications to certain clauses...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1974 - 1020 pages
...shall be allowed In arriving at the termination settlement. (d) If a Stop Work Order la not canceled and the work covered by such order Is terminated for...shall be allowed by equitable adjustment or otherwise. [37 PR 14940, July 26, 1972] § 18—7.106 Price escalation clauses (established prices). This § 18-7.106...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1972 - 1094 pages
...stoppage: Provided, That, if the Contracting Officer decides the facts Justify such action, he may receive and act upon any such claim asserted at any...under this contract. (c) If a Stop Work Order is not canceled and the work covered by such order is terminated, the reasonable costs resulting from the...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1976 - 1202 pages
...work stoppage; provided that, if the Contracting Officer decides the facts justify such action, he may receive and act upon any such claim asserted at any...prior to final payment under this contract. (c) If a Slop Work Order is not canceled and the work covered by such order is terminated, the reasonable costs...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1983 - 1104 pages
...the Contracting Officer decides the facts justify such action, he may receive and act upon any neb claim asserted at any time prior to final payment...under this contract. (c) If a Stop Work Order is not canceled and the work covered by such order is terminated, the reasonable costs resulting from the...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1980 - 582 pages
...asserted after this time, if the Contracting Officer decides the facts justify such action, he may receive and act upon any such claim asserted at any...time prior to final payment under this contract. (c) Failure to agree to any adjustment under paragraph (b) of this clause shall be a dispute concerning...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1978 - 944 pages
...Contracting officer decides the facts justify such action, he may receive and act upon any such claia asserted at any time prior to final payment under this contract. (c) If a stop work order is not canceled and the work covered by such order is terminated for th« convenience of the Government, the...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1981 - 662 pages
...Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive and act upon any such claim asserted at any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1966 - 1420 pages
...Provided, however, That the Contracting Officer, If he decides that the facts Justify such action, may receive and act upon any such claim asserted at any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meanIng...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1983 - 788 pages
...a stop-work order could not have been ascertained prior to written submission of the claim), he may receive and act upon any such claim asserted at any time prior to final payment under this grant. (e) If a stop-work order is not canceled and grant-related project work covered by such order...