" If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted by an act of the Contracting Officer in the administration of... "
Code of Federal Regulations: Containing a Codification of Documents of ... - Page 238
1977
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1979 - 712 pages
...adjustments. Insert the clause prescribed by FPR 1-7.102-20, modified as set forth in §9-7.102-20. ; 9-7.802-21 Suspension of work. SUSPENSION OF WORK...unreasonable suspension or delay, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1977 - 708 pages
...forth in FPR l-1.1310-2(a) under the conditions set in the manner prescribed therein. S9-7. 802-21 Suspension of work. SUSPENSION OF WORK (a) The contracting...unreasonable suspension or delay, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1982 - 704 pages
...FPR 1-7.102-20, modified as set forth in §9-7.102-20. §9-7.802-21 Suspension of work. SUSPENSION OP WORK (a) The Contracting Officer may order the architect-engineer,...unreasonable suspension or delay, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1984 - 788 pages
...regarding their status as minority business enterprises in lieu of an independent investigation. 18. SUSPENSION OF WORK (a) The Contracting Officer may...act within the time specified in this contract [or il no time is specified, within a reasonable time), an adiustment shall be made for any increase in...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1981 - 524 pages
...appropriate for the convenience of the Government. Ib) If the performance of all or any part of the wort is. for an unreasonable period of time, suspended...within a reasonable time), an adjustment shall be mate for any increase in cost of performance of this contract (excluding profit) necessarily caused...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1972 - 862 pages
...or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted by an act of the Contracting Officer in the administration...time), an adjustment shall be made for any increase In the cost of performance of this contract (excluding profit) necessarily caused by such unreasonable...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1981 - 662 pages
...or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted by an act of the Contracting Officer in the administration...time), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit! necessarily caused by such unreasonable...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1971 - 664 pages
...of the work is, for an unreasonable period of time, suspended, delayed, or interrupted by an act oí the Contracting Officer in the administration of this...time), an adjustment shall be made for any Increase in the cost of performance of this contract (excluding profit) necessarily caused by such unreasonable...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1967 - 2356 pages
...or any part of the work Is, for an unreasonable period of time, suspended, delayed, or interrupted by an act of the Contracting Officer In the administration...If no time Is specified within a reasonable time) , and adjustment shall be made for any Increase In the cost of performance of this contract (excluding...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1974 - 788 pages
...all or any pan of the work is. for an unreasonable period of time, suspended, delayed, or interrupted by an act of the Contracting Officer in the administration...time specified in this contract (or if no time is speciñed, within a reasonable time), an adjustment shall be made for any increase in the cost of performance...