Parliamentary Papers, Volume 16H.M. Stationery Office, 1962 - Bills, Legislative |
From inside the book
Results 1-3 of 78
Page 4
... January 1963 , the mean temperature throughout the month averaged 28 ° F. Extremely cold conditions continued during February when the average mean temperature was 31 ° F. The extra heating demands caused unit requirements in these ...
... January 1963 , the mean temperature throughout the month averaged 28 ° F. Extremely cold conditions continued during February when the average mean temperature was 31 ° F. The extra heating demands caused unit requirements in these ...
Page 68
... January and 30th November , 1961 , the network had been reinforced by the addition of 96 substations at a cost of £ 748,000 . Between 1st January and 30th November 1962 , in the same area , 244 new substations had been commissioned at a ...
... January and 30th November , 1961 , the network had been reinforced by the addition of 96 substations at a cost of £ 748,000 . Between 1st January and 30th November 1962 , in the same area , 244 new substations had been commissioned at a ...
Page 52
... January , 1963 , Mr. W. J. Guscott , who had recently succeeded Mr. E. Bates as Chief Commercial Engineer , was welcomed to the Council meeting . The Council heard from Mr. Guscott an interesting address on the Board's campaign , in ...
... January , 1963 , Mr. W. J. Guscott , who had recently succeeded Mr. E. Bates as Chief Commercial Engineer , was welcomed to the Council meeting . The Council heard from Mr. Guscott an interesting address on the Board's campaign , in ...
Other editions - View all
Common terms and phrases
1st April 33/11 kV substation additional Alderman amount annual apparatus APPENDIX appliances Area Boards Balance Sheet block storage Bulk Supply Tariff cables capital expenditure cent Central Electricity charges Circuit Miles Commercial Contracting and Sales cost Councillor Denbighshire Depreciation Deputy Chairman District Committees domestic EAST MIDLANDS ELECTRICITY EASTERN ELECTRICITY BOARD Electricity Act Electricity Consultative Council Electricity Council Electricity Generating Board Electricity Supply employees ended 31st March Farm financing Fixed Assets heating hire purchase increase industrial installation kilowatt kV transformers LONDON ELECTRICITY BOARD maximum demand meet Merseyside meter reading MIDLANDS ELECTRICITY BOARD million Minister of Power Montgomeryshire NORTH EASTERN ELECTRICITY North Western number of consumers off-peak Officers overhead line premises programme Public Lighting reinforcement Report Revenue Account Road rural Salaries sales of electricity Sales of Fittings scheme showrooms South Wales staff Statement storage heaters Street sumers Superannuation Tariff Underground unit sold voltage volts