Contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, in either its sovereign or contractual capacity, acts of another contractor in the performance of a contract with the Government, fires, floods,... Decisions of the Comptroller General of the United States - Page 147by United States. General Accounting Office - 1950Full view - About this book
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1958 - 1044 pages
...contractor charged with liquidated damages because of any delays in the completion of the work due to unforeseeable causes beyond the control and without...contractor in the performance of a contract with the Governmentj fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually... | |
| United States. Court of Claims - Law reports, digests, etc - 1946 - 906 pages
...contractor charged with liquidated damages because of any delays in the completion of the work due to unforeseeable causes beyond the control and without...the Government, acts of another contractor in the perfonnance of a contract with the Government, fires, floods, epidemics, quarantine restrictions, strikes,... | |
| United States. Court of Claims - Law reports, digests, etc - 1946 - 936 pages
...contractor charged with liquidated damages because of any delays in the completion of the work due to unforeseeable causes beyond the control and without...of the public enemy, acts of the Government, acts or another contractor in the performance of a contract with the Government, fires, floods, epidemics,... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1955 - 908 pages
...contractor charged with liquidated damages because of any delays in the completion of the work due to unforeseeable causes beyond the control and without...including, but not restricted to, acts of God, or of the pub245 Findings of Fact lie enemy, acts of the Government, acts of another contractor in the performance... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1952 - 1040 pages
...contractor charged with liquidated damages because of any delays In the completion of the work due to unforeseeable causes beyond the control and without...including, but not restricted to, acts of God, or the public enemy, acts of the Government, Including, but not restricted to any preference, priority... | |
| United States. Court of Claims - Law reports, digests, etc - 1942 - 818 pages
...any delays in the completion of the work due to unforseeable causes beyond the control and without the fault or negligence of the contractor, including,...God, or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe... | |
| United States. Court of Claims - Law reports, digests, etc - 1939 - 836 pages
...contractor charged with liquidated damages because of any delays in the completion of the work due to unforeseeable causes beyond the control and without...contractor, including, but not restricted to, acts of God, * * * and unusually severe weather * * *; 'Provided, further, That the contractor shall within 10 days... | |
| United States. Court of Claims - Law reports, digests, etc - 1937 - 786 pages
...unforesee*able causes beyond the control and without the fault or Reporter'i Statement of the Case negligence of the contractor, including, but not restricted...God, or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe... | |
| United States. Court of Claims - Law reports, digests, etc - 1948 - 886 pages
...liable for excess costs incurred when the delay or failure Opinion of the Court to deliver was due to unforeseeable causes beyond the control and without...of the contractor, including but not restricted to numerous named causes among which was unusually severe weather. Between September 7, 1942, and September... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1950 - 1004 pages
...of the Government (including, but not restricted to, any preference, priority or allocation order), acts of another contractor in the performance of a...floods, epidemics, quarantine restrictions, strikes * * *. ARTICLE 13. Other contracts. — The Government may award other contracts for additional work,... | |
| |