...claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1968 - 922 pages
...claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of...receive and act upon any such claim asserted at any time/prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1959 - 1028 pages
...in writing within 30 days from the date of receipt by the Contractor of the notification of extra or change : Provided, however, That the Contracting Officer,...upon any such claim asserted at any time prior to the date of final settlement of the contract. If the parties fail to agree upon the adjustment to be... | |
| Administrative law - 1982 - 690 pages
...claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of...Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's claim for adjustment, the Contracting Officer... | |
| Administrative law - 1982 - 988 pages
...Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor of the notification of...Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's claim for adjustment, the Contracting Officer... | |
| Administrative law - 1971 - 668 pages
...adjustment under this clauaeSmiwlie V-_ within 30 days from the date of receipt by the CctfijrWctor of the notification of change: Provided, however....Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's claim for adjustment, the Contracting Officer... | |
| Administrative law - 1981 - 524 pages
...claim by tht Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of...payment under this contract. Where the cost of property mad* obsolete or excess as a result of a change is included in the Contractor's claim for adjustment,... | |
| Administrative law - 1971 - 664 pages
...adjustment under this clauseNmiAL be ijseerted within 30 days from the date of receipt by the Cim)irector of the notification of change: Provided, however....Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's claim for adjustment, the Contracting Officer... | |
| Administrative law - 1972 - 862 pages
...clause must be asserted within 30 days from the date of receipt by the Contractor of the notlflcatlon of change: Provided, however, That the Contracting...Where the cost of property made obsolete or excess as a result of a change Is Included In the Contractor's claim for adjustment, the Contracting Officer... | |
| Administrative law - 1974 - 788 pages
...claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concernIng a question of fact within the meaning... | |
| |