...the Contractor shall be afforded an opportunity to be heard and to offer evidence in support of its appeal. Pending final decision of a dispute hereunder,...accordance with the Contracting Officer's decision. The plaintiff contends that the insolvency of its subcontractor made the contract impossible of performance... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1968 - 922 pages
...the Contractor shall be afforded an opportunity to be heard and to offer evidence in support of its appeal. Pending final decision of a dispute hereunder,...shall proceed diligently with the performance of the 544 Findincs of Fact contract and in accordance with the Contracting Officer's decision. * * * * *... | |
| United States. Congress. House. Committee on Armed Services - Legislative hearings - 1960 - 1930 pages
...heard and to offer evidence in support of its appeal. Pending final decision of a dispute hereumler, the Contractor shall proceed diligently with the performance...questions in connection with decisions provided for in paragraph (a) above: Provided, That nothing in this contract shall be construed as making final the... | |
| Administrative law - 1999 - 574 pages
...the Contractor shall be afforded an opportunity to be heard and to offer evidence in support of its appeal. Pending final decision of a dispute hereunder,...connection with decisions provided for in para graph (a) above: Provided, That nothing in this contract shall be construed as making final the decision of any... | |
| Administrative law - 1966 - 968 pages
...be afforded an opportunity to be heard and to offer evidence In support of Its appeal. Pending flnal decision of a dispute hereunder, the Contractor shall...questions in connection with decisions provided for In paragraph (a) of this section: Provided, That nothing in this contract shall be construed as making... | |
| Administrative law - 1969 - 420 pages
...the Contractor shall be afforded an opportunity to be heard and to offer evidence In support of its appeal. Pending final decision of a dispute hereunder,...consideration of law questions in connection with décisions provided for in paragraph (a) above: Provided, That nothing in this contract shall be construed... | |
| Administrative law - 1973 - 740 pages
...The Contractor shall be afforded an opportunity to be heard and to offer evidence In support of his appeal. Pending final decision of a dispute hereunder...."Disputes" clause does not preclude consideration of law questlo In connection with decisions provided for In (a) above; prov that nothing In this contract... | |
| Administrative law - 1979 - 1304 pages
...the Contractor shall be afforded an opportunity to be heard and to offer evidence in support of his appeal. Pending final decision of a dispute hereunder,...Disputes clause does not preclude consideration of questions of law in connection with decisions provided for in paragraph (a) above. Nothing in this... | |
| Administrative law - 1970 - 984 pages
...and to offer evidence in support of Its appeal. Fending final decision of a dispute hereunder, tin Contractor shall proceed diligently with the performance...questions in connection with decisions provided for In pangraph (a) of this section: Provided, That nothing In this contract shall be construed as making... | |
| Administrative law - 1974 - 686 pages
...shall be afforded an opportunity to be heard and to offer evidence in support of his appeal. Fending final decision of a dispute hereunder, the Contractor..."Disputes" clause does not preclude consideration of questions of law in connection with decisions provided for in paragraph a above: Provided, That nothing... | |
| |