| Administrative law - 1981 - 676 pages
...determined on such appeal. (h) In arriving at the amount due the Contractor under this clause there shall be deducted (1) all unliquidated advance or other...portion of this contract, (2) any claim which the Government may have against the Contractor in connection with this contract, and (3) the agreed price... | |
| Administrative law - 1994 - 1186 pages
..."Remedies" proceeding. (g) In arriving at the amount due the contractor under this clause there shall be deducted (1) all unliquidated advance or other...portion of this contract, (2) any claim which the owner may have against the contractor In connection with this contract, and (3) the agreed price for,... | |
| Administrative law - 1966 - 1420 pages
...determined on such appeal. (h) In arriving at the amount due the Contractor under this clause there shall be deducted (1) all unliquidated advance or other...applicable to the terminated portion of this contract, (11) any claim which the Government may have against the Contractor in connection with this contract,... | |
| Administrative law - 1967 - 2356 pages
...determined on such appeal. (h) In arriving at the amount due the Contractor under this clause there shall be deducted (1) all unliquidated advance or other...applicable to the terminated portion of this contract, (11) any claim which the Government may have against the Contractor In connection with this contract,... | |
| Administrative law - 1972 - 1094 pages
...determined on such appeal. (h) In arriving at the amount due the Contractor under this clause there shall be deducted : (1) All unliquidated advance or other...Contractor, applicable to the terminated portion of this Letter Contract; (ii) Any claim which the Government may have against the Contractor in connection... | |
| Administrative law - 1977 - 1240 pages
...determined on such appeal. (h) In arriving at the amount due the Contractor under this clause there shall be deducted (1) all unliquidated advance or other...Contractor, applicable to the terminated portion of this con ti act. (9) any claim which the Government may have against the Contractor in connection with this... | |
| Administrative law - 1975 - 1236 pages
...appeal. (hi In arriving at the amount due the Contractor under this clause there shall be deducted (i) all unliquidated advance or other payments on account...applicable to the terminated portion of this contract, (ii) any claim which the Government may have against the Contractor in connection with this contract,... | |
| Administrative law - 1980 - 976 pages
...appeal. (h) In arriving at the amount due the Contractor under this clause there shall be deducted: (i) all unliquidated advance or other payments on account...Contractor, applicable to the terminated portion of this Letter Contract; (ii) any claim which the Government may have against the Contractor in connection... | |
| Administrative law - 1983 - 782 pages
...Contractor under this clause there shall be deducted (1) all unliquidated advance or other payments theretofore made to the Contractor, applicable to...portion of this contract, (2) any claim which the Government may have against the Contractor in connection with this contract, and (3) the agreed price... | |
| Administrative law - 1974 - 1028 pages
...arriving at the amount due the Contractor under this clause there shall be deducted (i) all unhiquidated advance or other payments on account theretofore made to the Contractor, applicable to the termi-- nated portion of this contract, (ii) any claim which the Government may have against the Contractor... | |
| |