| Illinois. Supreme Court - Law reports, digests, etc - 1913 - 712 pages
...prosecution or completion of the work by the act, neglect or default of the owner, of the architect, or of any other contractor employed by the owner upon...equivalent to the time lost by reason of any or all the causes aforesaid, which extended period shall be determined and fixed by the architect; but no... | |
| Illinois. Supreme Court - Law reports, digests, etc - 1908 - 710 pages
...earthquake or cyclone, or by abandonment of the work by employees through no fault of the contractor, then the time herein fixed for the completion of the...shall be extended for a period equivalent to the time Iqst by reason of any or all of the causes aforesaid." Article 8 stipulates that the owner shall pay... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1955 - 908 pages
...the Contractor, or any other Subcontractor, through no default of the Subcontractor, then the time fixed for the completion of the work shall be extended for a period equivalent to the time lost by any or all of the causes aforesaid, but no such 501 Findings of Fact allowance shall be made unless... | |
| British Columbia - Law - 1913 - 696 pages
...other unavoidable causes, then the time herein fixed for the doing or completion of any such works shall be extended for a period equivalent to the time...lost by reason of any or all of the causes aforesaid. The period of such extension shall, if the City and Railway Company or the Canadian Northern Railway... | |
| Law reports, digests, etc - 1917 - 2042 pages
...or cyclone, or by the abandonment of the work by the employes through no fault of the subcontractor, then the time herein fixed for the completion of the...by reason of any or all of the causes aforesaid," etc. This provision makes it clear that delays occasioned the plaintiff by the owner, the general contractor,... | |
| Law reports, digests, etc - 1907 - 2094 pages
...lightning, earthquake or cyclone, or by strikes or lockouts, through no default of the contractor, then the time herein fixed for the completion of the...lost by reason of any or all of the causes aforesaid, but no such allowance shall be claimed or made unless a claim therefor shall be presented in writing... | |
| Law reports, digests, etc - 1905 - 1156 pages
...work by the act, neglect, delay, or default of the owner or the architects, » • • then the time fixed for the completion of the work shall be extended...lost by reason of any or all of the causes aforesaid, but no such allowance shall be made unless a claim therefor is presented in writing to the architects... | |
| Law reports, digests, etc - 1914 - 1134 pages
...architects or of any other contractor employed by the owner on the work, the time fixed for completion "shall be extended for a period equivalent to the...by reason of any or all of the causes aforesaid." But It was' also provided that "no such allowance will be made unless a claim thereof is presented... | |
| Law reports, digests, etc - 1902 - 1270 pages
...abandonment of the work by the employC-s of the contractor through no fault of theirs, then the time fixed for the completion of the work shall be extended for a period equivalent to the time thus lost," etc. It thus appears that the contractors stipulated what they might claim for themselves... | |
| Law reports, digests, etc - 1912 - 1356 pages
...prosecution or completion of the work by the act, neglect, or default of the owner or architect that the time herein fixed for the completion of the work shall be extended for a period equal to the time lost by reason of any such cause. But It also provides that no such allowance shall... | |
| |