| Law reports, digests, etc - 1920 - 956 pages
...comply with the provisions of the contract. The city, if not at fault, may give the contractor ten days' written notice; and at the end of that time,...if the contractor continues to neglect the work the city may * « « terminate the employment of the contractor under this agreement, and take possession... | |
| American Railway Engineering Association - Railroad engineering - 1914 - 1224 pages
...this contract. t- i Annulment. ' (b) The. Company, if not at fault, may give the Contractor ten (ip) days' written notice, and at the end of that time...terminate the employment of the Contractor under this agreeent and take possession of «bc;ipfeniises and of all materials, tools and appliances thereon,... | |
| Clinton Hamlin Blake - Architects - 1916 - 360 pages
...after giving the Contractor seven days' written notice, terminate the employment of the Contractor and take possession of the premises and of all materials, tools and appliances thereon and finish the work by whatever method he may deem expedient. In such case the Contractor shall not be... | |
| Fred Lavis - Railroads - 1917 - 648 pages
...provisions of this contract. Annulment. (b) The Company, if not at fault, may give the Contractor ten (10) days' written notice. and at the end of that time,...possession of the premises and of all materials, tools and applianees thereon, and employ such forces as may be necessary to finish the work. In such case the... | |
| Calvin Frank Allen - Commercial law - 1917 - 468 pages
...after giving the Contractor seven days' written notice, terminate the employment of the Contractor and take possession of the premises and of all materials, tools and appliances thereon and finish the work by whatever method he may deem expedient. In such case the Contractor shall not be... | |
| Calvin Frank Allen - Commercial law - 1917 - 472 pages
...after giving the Contractor seven days' written notice, terminate the employment of the Contractor and take possession of the premises and of all materials, tools and appliances thereon and finish the work by whatever method he may deem expedient. In such case the Contractor shall not be... | |
| Architecture - 1917 - 550 pages
...after giving the Contractor seven days. written notice, terminate the employment of the Contractor and take possession of the premises and of all materials, tools and appliances thereon and finish the work by whatever method he may deem expedient. In such case the-Contractor shall not be... | |
| Building - 1919 - 476 pages
...after giving the Contractor seven days' written notice, terminate the employment of the Contractor and take possession of the premises and of all materials, tools and appliances thereon and finish the work by whatever method he may deem expedient. In such case the Contractor shall not be... | |
| Calvin Frank Allen - Business law - 1919 - 486 pages
...after giving the Contractor seven days' written notice, terminate the employment of the Contractor and take possession of the premises and of all materials, tools and appliances thereon and finish the work by whatever method he may deem expedient. In such case the Contractor shall not be... | |
| American Institute of Architects - Architectural practice - 1920 - 212 pages
...after giving the Contractor seven days' written notice, terminate the employment of the Contractor and take possession of the premises and of all materials, tools and appliances thereon and finish the work by whatever method he may deem expedient. In such case the Contractor shall not be... | |
| |