B.-Detailed estimates of a canal lock, eight feet lift, new plan.

Grubbing and clearing.

Bailing and draining.

Excavation of earth, 15,044 cubic yards, at 30 cents.
Embankment, 3,000 cubic yards, at 30 cents.

Puddling earth in foundation, 600 cubic yards, at 20 cents
Masonry in lock walls, foundation, and section, 280 cubic
yards, at $12 50..

Masonry in four piers in gate chamber, 156 cubic yards, at
$7

Masonry in the breast of the lock, 102 cubic yards, at $5.
Pavement at the head of the lock, 87 cubic yards, at $2 25
Foundation timber, 12,000 feet, board measure, at 25 cents
Floor plank, three inches thick, 3,550 feet, board measure,
at 50 cents..

Gate timber plank, &c., pine, 4,639 feet, board measure, at
50 cents..
Foundation timber for second section, 72,000 feet, board
measure, at 25 cents..

Floor plank, of three inches thick, for second section,
25,200 feet, board measure, at 50 cents..

Floor plank, of two inches thick, for second section, 10,920 feet, board measure, at 50 cents..

Masonry in lock walls, second section, 1,568 cubic yards, at $12 50..

Masonry in third section, 368 cubic yards, at $12 50.. Masonry in four piers in gate section, 212 cubic yards, at $7

Masonry in lower chamber under side walls, 55 cubic yards, at $7..

Foundation timber, 12,890 feet, board measure, at 25 cents
Timber and plank for lower gate, 4,821 feet, board measure,
at 50 cents..

Bearing piles, in lineal feet, 4,500 lineal feet, at 20 cents..
Wrought iron for the first section, 4,141 pounds, at 15 cents
Wrought iron for the first section, 1,711 pounds, at 20 cents
Cast iron for the first section, 21,401 pounds, at 10 cents..
Wrought iron for the third or lower section, 3,565 pounds,
at 20 cents....

Wrought iron for the third or lower section, 3,491 pounds,
at 15 cents..

Cast iron for the third or lower section, 22,434 pounds, at 10 cents...

Screw-bolts and spikes for the whole lock, 3,000 pounds, at

15 cents...

[blocks in formation]

$200 00

1,500 00

4,513 20 900 00

120 00

3,500 00

1,092 00 510 00 195 75

300 00

1,775 00

231 95

1,800 00

1,350 00

546 00

19, 600 00

4,500 00

1,484 00

385 00

322 25

241 00

900 00

621 15

342 20 2,140 10

713 00

524 55

2,243 40

450 00

100 00

50 00

60 00

C.

Grubbing and clearing.

Bailing and draining..

53, 210 55

$200 00 1,500 00

Excavation of earth, 15,786 cubic yards, at 30 cents....
Embankment, 1,500 cubic yards, at 30 cents...

Masonry in the lock walls of first section, 280 cubic yards,
at $12 50..

Masonry in four piers in gate chamber, 156 cubic yards, at $7..

Rubble masonry in breast of the lock, 102 cubic yards, at
$5...

Pavement at the head of the lock, 87 cubic yards, at $2 50
Foundation timber, 12,000 feet, board measure, at 25 cents
Floor plank, of three inches thick, 3,550 feet, board meas-
ure, at 50 cents...

$4,735 80 450 00

3,500 00

1,092 00

510 00

217 50

300 00

177 50

Floor plank, of two inches thick, 2,000 feet, board measure, at 50 cents...

100 00

Timber and plank for the gate, 4,639 feet, board measure, at 50 cents..

Pavements of the sides and bottom, middle section, to be grouted with cement, 1,833 square yards, at $4.. Masonry in lock walls of third section, 400 cubic yards, at $12 50

231 95

7,332 00

5,000 00

Masonry in four piers of third section chamber, 212 cubic yards, at $7.....

1,484 00

Masonry return of walls at lower end, 55 cubic yards, at $12 50

685 50

Foundation timber in third section, 12,890 feet, board meas

ure, at 25 cents....

322 25

Floor plank, of three inches thick, third section, 5,400 feet, board measure, at 50 cents..

270 00

Floor plank, of two inches thick, third section, 3,600 feet, board measure, at 50 cents...

180 00

Timber and plank for the gate, third section, pine, 4,821 feet, board measure, at 50 cents...

241 00

Bearing piles, (lineal feet,) at 20 cents.

Wrought iron for first section, 4,141 pounds, at 15 cents..
Wrought iron for first section, 1,711 pounds, at 20 cents..
Cast iron for first section, 21,401 pounds, at 10 cents....
Wrought iron for third section, 3,565 pounds, at 20 cents..
Wrought iron for third section, 3,491 pounds, at 15 cents..
Cast iron, 22,434 pounds, at 10 cents...

Screw bolts and spikes, 2,000 pounds, at 15 cents..
Puddling earth in foundation, 300 cubic yards, at 20 cents
Materials for cement..

713 00

621 15

342 20

2, 140 00

713 00

524 55

2,243 40

300 00

60 00

200 00

[blocks in formation]

D.-Statement of canal and river improvements existing in the United States.

[graphic][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][ocr errors][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][ocr errors][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][ocr errors][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][ocr errors][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][ocr errors][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed][subsumed]

Name and State.

D.-Statement of canal and river improvements, &c.—Continued.

[blocks in formation]
[merged small][merged small][merged small][merged small][merged small][merged small][merged small][ocr errors][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][ocr errors][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small]

E.-Statement of canal and river improvements contemplated in the United States.

[blocks in formation]

F.-Names of some of the greatest navigable rivers in the United States.

Missouri River to the Great Falls...

Missouri River above Great Falls to the Three Forks.

Length in miles.

3, 150

150

[blocks in formation]

Platte River, (both forks,) North Fork to mouth of Sweet Water

400

River, South Fork to Denver.

Black Warrior River..

Rio Grande to mouth of Pecos River..

Pecos River...

1,060

200

550

450

The descent of many of these rivers was ascertained, but the information being too ine

it was omitted.

« PreviousContinue »