Decisions of the Comptroller General of the United States, Volume 55U.S. Government Printing Office, 1977 - Finance, Public Contains a selection of major decisions of the GAO. A digest of all decisions has been issued since Oct. 1989 as: United States. General Accounting Office. Digests of decisions of the Comptroller General of the United States. Before Oct. 1989, digests of unpublished decisions were issued with various titles. |
From inside the book
Results 1-5 of 100
Page 3
... basis , acted im- properly in failing to solicit other bidders on same basis , other bidders were not prejudiced since it is unlikely they would have offered surplus and low surplus bid was responsive to IFB . Contracts Specifications ...
... basis , acted im- properly in failing to solicit other bidders on same basis , other bidders were not prejudiced since it is unlikely they would have offered surplus and low surplus bid was responsive to IFB . Contracts Specifications ...
Page 24
... basis unless they know in advance the basis on which their bids will be evaluated . See 36 Comp . Gen. 380 ( 1956 ) ; DPF Incorporated , B - 180292 , September 12 , 1974 ; Grunley - Walsh Construction Company , Inc. , B - 181593 ...
... basis unless they know in advance the basis on which their bids will be evaluated . See 36 Comp . Gen. 380 ( 1956 ) ; DPF Incorporated , B - 180292 , September 12 , 1974 ; Grunley - Walsh Construction Company , Inc. , B - 181593 ...
Page 30
... basis to the low offeror , so long as the agency gave the other offerors an equal opportunity to compete on the same basis . In the present case , based on ASO's belief that Alden's bid was nonre- sponsive to the IFB by virtue of its ...
... basis to the low offeror , so long as the agency gave the other offerors an equal opportunity to compete on the same basis . In the present case , based on ASO's belief that Alden's bid was nonre- sponsive to the IFB by virtue of its ...
Page 31
... basis of the record before us , we believe that award could have been made under the IFB to Alden , notwithstanding ... basis with Alden had no reasonable basis , since , as indicated in detail above , ASO has stated that although the ...
... basis of the record before us , we believe that award could have been made under the IFB to Alden , notwithstanding ... basis with Alden had no reasonable basis , since , as indicated in detail above , ASO has stated that although the ...
Page 33
... basis . 44 Comp . Gen. , supra ; Ampex Corporation , supra . How- ever , 44 Comp . Gen. , supra , and Ampex Corporation , supra , do not stand for the proposition , as is suggested by ASO , that Military Specifications are not mandatory ...
... basis . 44 Comp . Gen. , supra ; Ampex Corporation , supra . How- ever , 44 Comp . Gen. , supra , and Ampex Corporation , supra , do not stand for the proposition , as is suggested by ASO , that Military Specifications are not mandatory ...
Other editions - View all
Common terms and phrases
49 Comp 54 Comp acceptable action administrative agency Air Force alleged amendment amount applicable appropriation Army ASPR authority award basis believe bid opening bid price bidder certifying officer claim clause competitive range concerning considered contends contracting officer contractor cost court decision Defense Military Department determination diem DLGN duty effect elastomer employee entitled evaluation expenses factors Federal funds furnished Government grant indicated involved issued July June June 30 Koehring letter mailgram matter ment mobile home NASA Navy negotiated nonresponsive offered offerors overtime payment performance personnel prior procedures Procurement Regulation proposal protest provides Public Law pursuant question reasonable receipt received regard reimbursement rejected request response retired schedule Secretary Service set-aside small business solicitation specific Stat statute statutory submitted supra technical tion transportation U.S. Code United VFAX