Decisions of the Comptroller General of the United States, Volume 55U.S. Government Printing Office, 1977 - Finance, Public Contains a selection of major decisions of the GAO. A digest of all decisions has been issued since Oct. 1989 as: United States. General Accounting Office. Digests of decisions of the Comptroller General of the United States. Before Oct. 1989, digests of unpublished decisions were issued with various titles. |
From inside the book
Results 1-3 of 3
Page 311
... VFAX development program . In- dustry responses were received in July 1974 . At this time , the VFAX program was meeting with some opposi- tion in the Congress , in part because the VFAX was not tied to the Air Force prototype program ...
... VFAX development program . In- dustry responses were received in July 1974 . At this time , the VFAX program was meeting with some opposi- tion in the Congress , in part because the VFAX was not tied to the Air Force prototype program ...
Page 312
... VFAX . Adaptation of the selected Air Force Air Combat Fighter to be capable of carrier operations is the prerequisite for use of the funds provided . Funds may be released to a contractor for the purpose of designing the modifications ...
... VFAX . Adaptation of the selected Air Force Air Combat Fighter to be capable of carrier operations is the prerequisite for use of the funds provided . Funds may be released to a contractor for the purpose of designing the modifications ...
Page 313
... VFAX . How- ever , as issued , it solicited proposals for the design , development , test and demonstration of the NACF . The RFQ called for a cost reimbursement type contract , incremen- tally funded in part , with proposals to be ...
... VFAX . How- ever , as issued , it solicited proposals for the design , development , test and demonstration of the NACF . The RFQ called for a cost reimbursement type contract , incremen- tally funded in part , with proposals to be ...
Other editions - View all
Common terms and phrases
49 Comp 54 Comp acceptable action administrative agency Air Force alleged amendment amount applicable appropriation Army ASPR authority award basis believe bid opening bid price bidder certifying officer claim clause competitive range concerning considered contends contracting officer contractor cost court decision Defense Military Department determination diem DLGN duty effect elastomer employee entitled evaluation expenses factors Federal funds furnished Government grant indicated involved issued July June June 30 Koehring letter mailgram matter ment mobile home NASA Navy negotiated nonresponsive offered offerors overtime payment performance personnel prior procedures Procurement Regulation proposal protest provides Public Law pursuant question reasonable receipt received regard reimbursement rejected request response retired schedule Secretary Service set-aside small business solicitation specific Stat statute statutory submitted supra technical tion transportation U.S. Code United VFAX