Decisions of the Comptroller General of the United States, Volume 55U.S. Government Printing Office, 1977 - Finance, Public Contains a selection of major decisions of the GAO. A digest of all decisions has been issued since Oct. 1989 as: United States. General Accounting Office. Digests of decisions of the Comptroller General of the United States. Before Oct. 1989, digests of unpublished decisions were issued with various titles. |
From inside the book
Results 1-5 of 100
Page 30
... Plan B ) of MIL- I - 27193B ( USAF ) , which would be harmful or destructive to the indicators tested . ( Since the initial contract quantity was less than 15 , " Sampling Plan B " tests would not seem to be required for this initial ...
... Plan B ) of MIL- I - 27193B ( USAF ) , which would be harmful or destructive to the indicators tested . ( Since the initial contract quantity was less than 15 , " Sampling Plan B " tests would not seem to be required for this initial ...
Page 34
... Plan B " tests would not appear to be required . ) We also note that ASO has previously indicated that 5 of the required " Sampling Plan A❞ tests were not going to be performed by Alden , although Alden has indicated that it performed ...
... Plan B " tests would not appear to be required . ) We also note that ASO has previously indicated that 5 of the required " Sampling Plan A❞ tests were not going to be performed by Alden , although Alden has indicated that it performed ...
Page 71
... plan was considered tech- nically inferior in that it contained no breakdown of individual tasks to be performed or a schedule for performing them , even though an acceptable management plan was an important aspect of the total proposal ...
... plan was considered tech- nically inferior in that it contained no breakdown of individual tasks to be performed or a schedule for performing them , even though an acceptable management plan was an important aspect of the total proposal ...
Page 84
... plan to support its assertions in this regard . In its cost analysis , FEA made a detailed comparison between the direct labor and the direct labor costs proposed by each of the offerors in the competitive range resulting in the ...
... plan to support its assertions in this regard . In its cost analysis , FEA made a detailed comparison between the direct labor and the direct labor costs proposed by each of the offerors in the competitive range resulting in the ...
Page 140
... Plan ( AAA Plan ) in the areas of employment and utilization of minority subcontractors . The KCATA's plan for utilization of minority subcontractors was based on a set - aside of eight craft areas for minority business . Under part I ...
... Plan ( AAA Plan ) in the areas of employment and utilization of minority subcontractors . The KCATA's plan for utilization of minority subcontractors was based on a set - aside of eight craft areas for minority business . Under part I ...
Other editions - View all
Common terms and phrases
49 Comp 54 Comp acceptable action administrative agency Air Force alleged amendment amount applicable appropriation Army ASPR authority award basis believe bid opening bid price bidder certifying officer claim clause competitive range concerning considered contends contracting officer contractor cost court decision Defense Military Department determination diem DLGN duty effect elastomer employee entitled evaluation expenses factors Federal funds furnished Government grant indicated involved issued July June June 30 Koehring letter mailgram matter ment mobile home NASA Navy negotiated nonresponsive offered offerors overtime payment performance personnel prior procedures Procurement Regulation proposal protest provides Public Law pursuant question reasonable receipt received regard reimbursement rejected request response retired schedule Secretary Service set-aside small business solicitation specific Stat statute statutory submitted supra technical tion transportation U.S. Code United VFAX