" The Contractor shall promptly, and before such conditions are disturbed, notify the Contracting Officer in writing of: (1) subsurface or latent physical conditions at the site differing materially from those indicated in this contract, or (2) unknown... "
Code of Federal Regulations: Containing a Codification of Documents of ... - Page 256
1964
Full view - About this book

The Code of Federal Regulations of the United States of America ..., Book 2

Administrative law - 1939 - 1306 pages
...differing from those shown on the drawings or Indicated In the specifications, or unknown conditions of an unusual nature differing materially from those...and generally recognized as Inhering In work of the chara:ter provided for In the plans and specifications, the attention of the contracting officer shall...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 110

United States. Court of Claims - Law reports, digests, etc - 1948 - 818 pages
...obvious to both parties that plaintiff had encountered changed and unforeseen subsurface conditions of an unusual nature differing materially from those...encountered and generally recognized as inhering in embankment construction work of the character covered by the contract and which conditions had not...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1972 - 862 pages
...shall be allowed if asserted after final payment under this contract. 4. DIFFERING SITE CONDITIONS (a) The Contractor shall promptly, and before such conditions...an unusual nature, differing materially from those ordinarilyencountered and generally recognized as inhering in work of the character provided for in...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1981 - 524 pages
...shall be allowed if asserted after final payment under this contract. 4. DIFFERING SITE CONDITIONS (a) The Contractor shall promptly, and before such conditions...indicated in this contract, or (2) unknown physical condition* at the site, of an tin* usual nature, differing materially from those ordinarily encountered...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1969 - 258 pages
...construction contracts. (a) Contract provisions. Cause 4 of Standard Form 23A provides that the sontractor shall promptly, and before such conditions are disturbed,...site differing materially from those Indicated in the contract, or (2) unknown physical conditions at the site Df an unusual nature, differing materially...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1989 - 884 pages
...notify the owner in writing of: (1) Subsurface °r latent physical conditions at the site differ ing materially from those indicated In this contract,...ordinarily encountered and generally recognized as In hering in work of the character provided for in this contract. The owner shall prompt;! Investigate...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1984 - 788 pages
...shall be allowed if asserted after final payment under this contract. 4. DIFFERING SITE CONDITIONS (a) The Contractor shall promptly, and before such conditions...(1) Subsurface or latent physical conditions at the sit* dilFi'ii i£ materially from those indicated in this contract, or (?.) unknown physical condition*...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1994 - 690 pages
...to the Contracting Officer of (1) subsurface or latent physical conditions at the site which differ materially from those Indicated In this contract,...physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering In work...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1982 - 784 pages
...subagreements.) (a) The contractor shall promptly, and before such conditions are disturbed, notify the recipient in writing of: (1) subsurface or latent physical conditions...differing materially from those indicated in this subagreement, or (2) unknown physical conditions at the site, of an unusual nature, differing materially...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1991 - 676 pages
...to the Contracting Officer of (1) subsurface or latent physical conditions at the site which differ materially from those Indicated In this contract,...physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as Inhering In work...