Owner shall be at liberty, after three days written notice to the Contractor , to provide any such labor or materials, and to deduct the cost thereof from any money then due or thereafter to become due to the Contractor under... Michigan Reports: Cases Decided in the Supreme Court of Michigan - Page 225by Michigan. Supreme Court, Randolph Manning, George C. Gibbs, Thomas McIntyre Cooley, Elijah W. Meddaugh, William Jennison, Hovey K. Clarke, Hoyt Post, Henry Allen Chaney, William Dudley Fuller, John Adams Brooks, Marquis B. Eaton, Herschel Bouton Lazell, James M. Reasoner, Richard W. Cooper - 1898Full view - About this book
| Michigan. Supreme Court, Randolph Manning, George C. Gibbs, Thomas McIntyre Cooley, Elijah W. Meddaugh, William Jennison, Hovey K. Clarke, Hoyt Post, Henry Allen Chaney, William Dudley Fuller, John Adams Brooks, Marquis B. Eaton, Herschel Bouton Lazell, James M. Reasoner, Richard W. Cooper - Law reports, digests, etc - 1919 - 806 pages
...the architect, the owners shall be at liberty, after three days' written notice to the contractor, to provide any such labor or materials, and to deduct...money then due or thereafter to become due to the contractor under this contract; and if the architect shall certify that such refusal, neglect or failure... | |
| Michigan. Supreme Court, Randolph Manning, George C. Gibbs, Thomas McIntyre Cooley, Elijah W. Meddaugh, William Jennison, Hovey K. Clarke, Hoyt Post, Henry Allen Chaney, William Dudley Fuller, John Adams Brooks, Marquis B. Eaton, Herschel Bouton Lazell, James M. Reasoner, Richard W. Cooper - Law reports, digests, etc - 1916 - 804 pages
...certified by the architect, the owner shall be at liberty after 48 hours' written notice to the contractor to provide any such labor or materials and to deduct...money then due, or thereafter to become due, to the contractor, under the contract, and if the architect shall certify that such refusal, neglect or failure... | |
| Marcus Tullius Hun - Law reports, digests, etc - 1893 - 724 pages
...part herein contained, such refusal, neglect or failure being certified by the architect, the owner shall be at liberty, after three days' written notice...become due to the contractors under this contract. And if the architect shall certify that such refusal, neglect or failure is sufficient ground for such... | |
| Law reports, digests, etc - 1922 - 1138 pages
...by the architect, the owner shall be at liberty, after three days' written notice to the contractor, to provide any such labor or materials, and to deduct...money then due or thereafter to become due to the contractor under this contract, and if the architect <f;=For other cases see same topic and KEY-NUMBER... | |
| Law reports, digests, etc - 1912 - 1170 pages
...the architect, the owner shall be at liberty after five days (5) written notice to the contractor, to provide any such labor or materials, and to deduct...money then due or thereafter to become due to the contractor under this contract ; and If the architect shall certify that such refusal, neglect or failure... | |
| Law reports, digests, etc - 1914 - 1230 pages
...liberty, after three days' written notice to the contractors, to provide all such labor or materials and deduct the cost thereof from any money then due or thereafter to become due the contractors under this contract ; and if the architects shall certify that such refusal, neglect... | |
| Law reports, digests, etc - 1913 - 1236 pages
...written notice to the contractor, to provide any such labor and materials, and to deduct the costs thereof from any money then due, or thereafter to become due, to the contractor under this contract ; and If the architects shall certify that such refusal, neglect, or... | |
| Law reports, digests, etc - 1895 - 1150 pages
...part herein contained, such refusal, neglect, or failure being certified by the architect, the owner shall be at liberty, after three days' written notice...become due to the contractors under this contract; and, if the architect shall certify that such refusal, neglect or failure is sufficient ground for... | |
| Law reports, digests, etc - 1908 - 1134 pages
...the architects, the owner shall be at liberty, after three days' written notice to the contractor, to provide any such labor or materials, and to deduct...money then due or thereafter to become due to the contractor under this contract ; and If the architects shall certify that such refusal, neglect, or... | |
| Law reports, digests, etc - 1908 - 1148 pages
...certified by the architect, the owner shall be at liberty after ten days' written notice to the contractor to provide any such labor or materials, and to deduct...money then due or thereafter to become due to the contractor under this contract. And, If the architect shall certify that such refusal, neglect, or... | |
| |